A carpenter was hired to build 192 window frames. The first day he made 5 frames and each day, thereafter he made 2 more frames than he made the day before. How many days did he take to finish the job?

1 Answer

+1 vote
by (49.4k points)
selected by
 
Best answer

Let the carpenter take n days to finish the job.

To Find: n

He builds 5 frames on day 1, 7 on day 2, 9 on day 3 and so on.

So it forms an AP 5, 7, 9, 11,… and so on.

We need to find the number of terms in this AP such that the sum of the AP will be equal to 192

Given: Sum of AP = 192

He finishes the job in 16 days.

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.

...