Correct Answer - Option 3 : 9
Given:
Time taken by 5 men to build a wall = 12 days
Formula used:
(M1 × D1)/W1 = (M2 × D2)/ W2
Calculation:
Let the work size of the wall = 100
⇒ The size of the wall 50% more than the original wall = 100 × 150/100 = 150
Let the men required to build the 50% more than the original wall = a
(5 × 12)/100 = (a × 10)/150
⇒ 60/100 = 10a/150
⇒ 3/5 = a/15
⇒ 3/1 = a/3
⇒ a = 9
∴ The required no of men = 9