Correct Answer - Option 2 : 16 days
Given
They complete the work together = 6 days
Formua Used
Work = time × efficiency
Calculations:
Suppose X, Y and Z take x, x/3 and x/4 days respectively to finish the work.
Then, one days work by them
⇒ (1/x + 3/x + 4/x) = 1/6
⇒ 8/x = 1/6
⇒ x = 48
⇒ Y takes days to finish the work. = 48/3 = 16
∴ The required answer is 16 days