8 people do one job in 25 days, then in how many days will 10 people do the same work?
1. 15
2. 18
3. 20
4. 21

1 Answer

0 votes
by (114k points)
selected by
 
Best answer
Correct Answer - Option 3 : 20

Given:

People1 = 8  ,  days1 = 25 

People2 = 10 ,  days = ?

Formula used:

Man1 × Day1 = Man2 × Day2

Calculation:

8 × 25 = 10 × Days

⇒ days = 200/10 = 20

∴ The required days is 20 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.