Correct Answer - Option 3 : 32 days
Given:
24 men can complete a job in 48 days
Formula used:
m1 × d1 = m2 × d2
m = number of men
d = number of days
Calculation:
According to the question:
24 × 48 = 36 × d2
⇒ d2 = 32
∴ 36 men will complete the job in 32 days.