in Mathematics by (5.7k points)

If a task is completed in 20 days by 5 workers, how long will it take 10 workers to perform the same task?

Please log in or register to answer this question.

2 Answers

0 votes
by (5.7k points)

Let the number of days for 10 workers to complete the task be x.

\(\frac{5}{10} = \frac{20}{x}\)

Cross-multiply

5x = 10 × 20

Simplify.

x = \(\frac{10 \times 20}{5}\)

x = 40

Therefore, 10 workers will require 40 days to complete the same task.

0 votes
by (15.6k points)

PrashantNayak, hello

Think about your answer, does it make sense?  We have more workers and now it takes longer to get the job done?!

The correct answer is 10 days.

5:10 = X:20

=> 10xX = 5x20

=> x = 5x20/10 = 10 days

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.