GVR Ltd. is engaged in manufacturing machine components. The target production is 200 units per day. The company had been successfully attaining this target until two months ago. Over the last two months, it has been observed that daily production varies between 150-170 units.

1. Identify the management function to rectify the above situation.

2. Briefly state the procedure to be followed so that the actual production may come up to the target production.

1 Answer

+1 vote
by (24.0k points)
selected by
 
Best answer

1.The controlling function of management is needed to rectify the above situation.

2. The procedure to be followed so that the actual production may come up with the target production is as follows:

(A) Providing training to workers if the workers are not well versed with the production process.

(B) Improving the work environment if it is not conducive to efficient working.

(C) Ensuring timely availability of the raw materials and other equipment if they are not made available on time.

(D) Replacing the machinery if it is defective or has become obsolete

Welcome to Sarthaks eConnect: A unique platform where students can interact with teachers/experts/students to get solutions to their queries. Students (upto class 10+2) preparing for All Government Exams, CBSE Board Exam, ICSE Board Exam, State Board Exam, JEE (Mains+Advance) and NEET can ask questions from any subject and get quick answers by subject teachers/ experts/mentors/students.